REPRESENTATIVE PROFESSIONAL EXPERIENCE
Property Assessment
Preparation of Phase I and II environmental assessments for the property -
- Review all leases and other documents to maintain an environmental indemnification.
- Prepare facility Health and safety Plans.
- Oversee geotechnical soil borings including sampling and analysis for chemical and physical parameters.
- Oversee the excavation, transpiration, & the staging , sampling, analyzing, and reporting of all soil excavation projects related to new equipment or floor repairs.
- Prepare Work Plans for all new building and equipment expansion projects to satisfying a Consent Agreement with U.S. EPA and PADEP.
Asbestos / Lead Abatement
Supervise Asbestos Abatement crew -
- 14 month removal operation.
- Excavation and removal of unknown drums and asbestos pipe lagging.
- Responsibilities included heavy equipment operation and field supervision.
Agency / Responsible Party Negotiation
Coordination of legal and technical meetings with and between -
- The Nineteen Settling Companies.
- The U.S. EPA,
- The Ohio EPA,
- The Company's remedial prime contractor,
- Review and approve invoices submitted by the Company's remedial prime contractor.
- Review all work Plans and other documents related to the Project,
- The Remedial Investigation,
- The Feasibility Study
- The Record of Decision
UST
Researched, developed and contracted -
- The removal of three (3) 4,000 gallon underground fuel oil storage tanks.
- The underground storage tanks were removed,
- Then replaced with one (1) diked, 9,000 gallon above ground storage tank.
- Over pressure shut off valves and other safe guards for pumping fuel oil were incorporated in the design.
Industrial Services
Designed and implemented -
Installation of new tube mill facility including:
- Plant layout, buildings,
- Weld plants,
- Handling equipment,
- Ultrasonic testing equipment,
- Straightening and cutting equipment,
- And ancillary equipment such as compressor air and cooling water systems.
Design Engineered, Designed and Approved -
Installation of complete Titanium Melting Shop including
- Buildings,
- Overhead cranes,
- Vacuum arc furnaces,
- Copper crucible cleaning machine,
- Vacuum weld chamber,
- Vacuum pumps,
- Cooling water systems,
- Compressed air systems,
- Concrete furnace bunkers and foundations.
SITE CHARACTERIZATION / REMEDIATION
Site charecterization and remediation of -
- Mixed wastes from the uranium mill operation,
- Demolition and decontamination of process equipment,
- Removal and eventual on-site burial in the tailings pile,
- Budget management as well as project management.
Provided over site of -
- Site sampling and charecterization of mixed wastes from a uranium mill operation,
- Draining and containerizing of mechanical fluids from mill equipment,
- Decontamination and demolition of yellow cake ovens,
- Remediation of chemical process vats,
- Field work and supervision
RADIOLOGICAL
Environmental Health and Safety oversite at a Department of Energy Decommissioning Project -
- Sampling and waste profiles for mixed wastes leading to disposal,
- Routine safety and industrial hygiene monitoring,
- Environmental evaluations of contaminated debris to meet off-site disposal site's waste acceptance criteria,
- Modifications and revisions to RCRA Part B Permit for mixed and PCB wastes,
- Field supervision, sampling, and reporting in support of free-release of areas and equipment,
- Oversite of major equipment removal,
- Sampling and reporting in compliance with NPDES Permit requirements,
- Generate and review Work Instruction Packages and Operations Work Requests for decommissioning activities.
|